Background documentationMaster Data for Scheduling

 

In the following master data objects, you enter the calendars and execution times that are relevant for the scheduling of order documents (for example, of planned replenishment orders, replenishment orders, and advanced shipping notifications) in SAP Supply Network Collaboration (SAP SNC):

  • In the ship-from location and in the product master for the ship-from location product (for processes on the supplier side)

  • In the transportation lane (for the shipment)

  • In the customer location and in the customer location product (for the goods receipt at the customer)

The following table provides an overview.

Activity

Master Data Object

Data

Order processing 1)

Ship-from location

VMI General tab page

Order processing time

Transportation lane

Header data

Calendar for order processing

Transportation planning 1)

Ship-from location product

GR/GI tab page

Transportation lead time

Ship-from location

Calendar tab page

Shipping calendar

Picking and packing 1)

Ship-from location product

GR/GI tab page

Pick/pack time

Ship-from location

Calendar tab page

Shipping calendar

Loading 1)

Ship-from location product

GR/GI tab page

Loading time = goods issue processing time - pick/pack time

The pick/pack time must be shorter than the goods issue processing time.

Ship-from location

Calendar tab page

Shipping calendar

Goods issue 2)

Ship-from location

Calendar tab page

Shipping calendar

Ship-from location product

GR/GI tab page

Goods issue processing time

Shipment

Means of transport in the transportation lane between ship-from location and customer location

Transportation duration

Transportation calendar

Goods receipt

Customer location

Calendar tab page

Receiving calendar

Customer location product

GR/GI tab page

Goods receipt processing time 3)

1) Only relevant for the scheduling schema VMIPLANNING.

2) Only relevant for the scheduling schema PLANNING.

3) In case of scheduling schema PLANNING is applied, and delivery date is used as the base date for replenishment planning: For the combinations of supplier, customer location, and product, where delivery date has been defined as the base date for replenishment planning, goods receipt processing time is considered 0 by the scheduling logic, regardless of the value entered in the master data.