In the following master data objects, you enter the calendars and execution times that are relevant for the scheduling of order documents (for example, of planned replenishment orders, replenishment orders, and advanced shipping notifications) in SAP Supply Network Collaboration (SAP SNC):
In the ship-from location and in the product master for the ship-from location product (for processes on the supplier side)
In the transportation lane (for the shipment)
In the customer location and in the customer location product (for the goods receipt at the customer)
The following table provides an overview.
Activity | Master Data Object | Data |
---|---|---|
Order processing 1) | Ship-from location
| Order processing time |
Transportation lane Header data | Calendar for order processing | |
Transportation planning 1) | Ship-from location product
| Transportation lead time |
Ship-from location
| Shipping calendar | |
Picking and packing 1) | Ship-from location product
| Pick/pack time |
Ship-from location
| Shipping calendar | |
Loading 1) | Ship-from location product
| Loading time = goods issue processing time - pick/pack time The pick/pack time must be shorter than the goods issue processing time. |
Ship-from location
| Shipping calendar | |
Goods issue 2) | Ship-from location
| Shipping calendar |
Ship-from location product
| Goods issue processing time | |
Shipment | Means of transport in the transportation lane between ship-from location and customer location | Transportation duration Transportation calendar |
Goods receipt | Customer location
| Receiving calendar |
Customer location product
| Goods receipt processing time 3) |
1) Only relevant for the scheduling schema VMIPLANNING
.
2) Only relevant for the scheduling schema PLANNING
.
3) In case of scheduling schema PLANNING
is applied, and delivery date is used as the base date for replenishment planning: For the combinations of supplier, customer location, and product, where delivery date has been defined as the base date for replenishment planning, goods receipt processing time is considered 0 by the scheduling logic, regardless of the value entered in the master data.