Editing the Simulation Version
You can do the following with a simulation version that you created with the directly invoked detailed scheduling planning board (DS planning board) or the resource planning table:
· Process it further using the detailed scheduling planning board or the resource planning table
· Incorporate it in the planning version if necessary
· Copy it and save it under another name
· Delete it

You work
simulatively on the DS planning board and the resource planning table on the
basis of the planning version for which you have invoked the DS planning board
or the resource planning table. On the directly invoked DS planning board and
the resource planning table, you can explicitly save the simulative planning
under a certain name as a simulation version for the planning version. You can
compare simulation versions with the
plan monitor or
using the DS
evaluations for example.
Because you have
the option of selecting further objects during the application via
Extend Selection…, the system not only applies the data from the work
area to select the objects, but also takes any temporary settings into account
when it loads a simulation version.
· If you have not changed the settings from the work area on the initial screen, the system uses the data from the work area to determine the objects.
· The system uses the sets that exist at the time of saving for the simulation version.
¡ All sets that you have changed, deleted, or added on the initial screen of the detailed scheduling planning board or resource planning table.
¡
All sets that you selected in addition to
the selection via the work area via
Extend Selection during the
application.
· If you saved the temporary data as a new work area, the system determines the selection of the objects for the simulation version via the new work area.
...
1. Starting from the SAP Easy Access Supply Chain Management screen, choose Advanced Planning and Optimization → Production Planning → Interactive Production Planning → Detailed Scheduling → Simulation Version.
2. Choose the desired simulation version.
3. Choose the desired function.
Function |
Use |
|
You use this function to continue processing the simulation version with the DS planning board. For more information, see Scheduling with the Detailed Scheduling Planning Board. |
Process in tabular form |
You use this function to process the simulation version with the resource planning table. For more information, see Scheduling with the Resource Planning Table. |
|
You choose this function If you want to incorporate planning data from the simulation version into the planning version For more information, see Adopting or Saving the Simulation Version. |
|
If you choose this function, a dialog box appears in which you can enter the name you want to use to save the simulation version. |
|
You use this function to delete a simulation version. |
4.
The system performs
the chosen function and invokes the detailed scheduling planning board or the
resource planning table with the simulation version.

In connection with Edit and
Adopt, you should note that simulation versions quickly become obsolete
if the planning in the planning version changes rapidly.
Adopting or Saving a Simulation Version
Updating the Simulation Version