Show TOC Start of Content Area

Query History of Manually Changed Order Proposals  Locate the document in its SAP Library structure

Technical Name: 0FRE_C06_Q0001

Use

Use this query to analyze manual changes made to automatically-created order proposals (OPs). This query shows the scale and the frequency of the changes made to the order proposals. The changes to OP quantities and release dates are captured in this query. 

You can also display stock exceptions (understocks, lost sales, undelivered products and overstocks) that occurred in the days after you made changes to the specific order proposal line(s).

This information shows the results that the manual change(s) had on the supply chain process for a store or distribution center (DC). In order to display the stock exception information, you can go from the history of manually changed OPs to the stock exception query (see: Number of Stock Exceptions).

The lowest level of detail displayed in the history of manually changed OPs represent: product, location, and calendar day values (OP line item changes).

The following key figures are derived from the differences between the manually changed and automatically generated quantities and delivery dates:

Note

You can jump to another query from a detail line or summary line of this query. You can do that, for example, to display the number of stock occurrences (understocks, lost sales, overstocks, and so forth) that occurred in the following 15 days after the OP change(s). See the query: Number of Stock Exceptions).

The second query will display the stock exceptions that occurred in the following 15 days after the OP manual change. If required, you can jump from that query to the individual stock exception queries to display detail information on: understock, lost sales, undelivered product, or overstocks.

 

You can drill down for additional information, as well as filter the information in the query by the following additional characteristics:

 

These variables enable you to enter a selection range of days, products and locations.

(belongs to variables used).

 

The following KPIs (key performance indicators) and key figures are calculated within this query:

Calculated Key Figures:

 

Query Formulas:

The following KPIs and key figures are displayed in this query:

 

Filter

InfoObject

Description of the InfoObject (or restriction or calculation formula)

N/A

 

Free Characteristics

InfoObject

Name

0PLANT__0PLANTCAT

Location Type

0VENDOR

Vendor

0SUPP_PLANT

Supplying Plant

0MATERIAL__0MATL_GROUP

Merchandise Category

0MATERIAL__ORPA_WGH1

Merchandise Category Level 1

0MATERIAL__ORPA_WGH2

Merchandise Category Level 2

0MATERIAL__ORPA_WGH3

Merchandise Category Level 3

0MATERIAL__ORPA_WGH4

Merchandise Category Level 4

0MAT_PLANT__0FRE_PLNPUR

Replenishment Planner

0FRE_OPSTAT

Order Proposal Release Status

0FRE_OPREAS

Order Proposal Change Reason

Variables Used

Variable

Name

0I_DAYS

(required) Period From/To (in Calendar Days)

0S_PROD

Product

0S_LOC

Location

Rows

InfoObject

Description of the InfoObject (or restriction or calculation formula)

0CALDAY

Calendar Day

0MATERIAL

Product

0PLANT

Location

0FRE_OPNO

Order Proposal Number

0FRE_OPITNO

Order Proposal Item Number

Columns

InfoObject

Description of the InfoObject (and restriction or calculation formula)

0FRE_OPOQTY

Order Proposal Original Quantity

0FRE_OPCQTY

Order Proposal Changed Quantity

0FRE_C06_CK001

Absolute Difference of Quantity Change – (Calculated Key Figure)

 

Absolute Difference of Quantity Change = ABS (‘OP Original Quantity’ – ‘OP Changed Quantity’)

0FRE_C06_CK002

Percentage Difference of Quantity Change – (Calculated Key Figure)

Percentage Difference of Quantity Change = (‘OP Changed Quantity’ – ‘OP Original Quantity’) %A ‘OP Original Quantity’)

0FRE_OPODEL

Order Proposal Original Delivery Date

Properties: Suppress Results

0FRE_OPCDEL

Order Proposal Changed Delivery Date

Properties: Suppress Results

0FRE_C06_CK003

Absolute Difference of Date Change – (Calculated Key Figure)

Absolute Difference of Date Change = ABS (‘OP Orig.Delivery Date’ – ‘FRE OP Chg. Deli.Date’)

Properties: Calculate Results as = Average of All Values

 

Report Report Interface

Query

Name

Number of Stock Exceptions

0FRE_MC01_Q0001

 

End of Content Area