Purchase Order Alerts
Purchase order alerts indicate that an exception situation has occurred connected to a purchase order in purchase order collaboration in SAP Supply Network Collaboration (SAP SNC).
The alert types are not relevant for the alert monitor in the shortage analysis of Service Parts Planning (SPP).
To generate a purchase order alert, the following options are available, depending on the alert type:
The Post Processing Framework (PPF) generates the alert. System administration can deactivate alert generation in the PPF.
SAP SNC generates the alert in the background taking into account the PPF configuration.
Note
If you have set the PO_PPF_EXEC
validation check to inactive, so that certain alerts are generated in the background, you can deactivate the generation of each alert type individually by setting the Inactive
flag for the alert in the relevant PPF action profile.
System administration executes a report regularly in the SAP SNC system. To call the report for online processing, on the SAP Easy Access
screen, choose .
SAP SNC generates the alert during validation of the purchase order. System administration can deactivate alert generation in Customizing for Validation
. For more information about validation of purchase orders, see Validation in Purchase Order Collaboration.
The following table contains the alert types for purchase order collaboration:
Alert Type | Alert Type ID | Source | Description |
|---|---|---|---|
Exception during validation of purchase order |
| Validation | SAP SNC detected a problem during validation. This alert is a general validation alert. Some validations generate more specific alerts (see below). |
Purchase order rejected |
| PPF or Background | The supplier manually rejected the purchase order on the purchase order collaboration Web UI. If the |
Purchase order item rejected |
| PPF or Background | The supplier manually rejected the purchase order item on the purchase order collaboration Web UI. If the |
Overdelivery tolerance exceeded |
| Validation | The total confirmed quantity of the purchase order item is greater than the total requested quantity of the purchase order item plus the overdelivery tolerance. The total confirmed quantity of the item is the sum of the confirmed quantities from the confirmation schedule lines of the This alert is generated by the If unlimited overdelivery is defined for the purchase order item, the system does not generate this alert. |
Underdelivery tolerance not reached |
| Validation | The total confirmed quantity of the purchase order item is less than the total requested quantity of the purchase order item minus the underdelivery tolerance. The total confirmed quantity of the item is the sum of the confirmed quantities from the confirmation schedule lines of the This alert is generated by the |
New purchase order item |
| Validation | The customer has sent a purchase order containing a new purchase order item to SAP SNC from his or her back-end system. This system generates this alert in the background. The |
Changed purchase order item |
| Validation | The customer has changed a purchase order item in his or her back-end system and sent the modified purchase order to SAP SNC. The alert text indicates what has changed (for example, the quantity or the date/time). For more information, see Processing of Changed Purchase Order Items. The system generates this alert in the background. The |
Partially confirmed purchase order item |
| PPF or Background | The total confirmed quantity for a purchase order item is less than the total requested quantity of the purchase order item. If the The total confirmed quantity of the item is the sum of the confirmed quantities from the confirmation schedule lines of the |
Late confirmation of purchase order item |
| PPF or Background | The confirmed delivery date of at least one confirmation schedule line lies after the delivery date requested by the customer. If the |
Manual approval of confirmation required |
| PPF or Background | This alert is relevant for purchase order collaboration with approval process. The customer must accept the confirmation schedule line manually on the purchase order collaboration Web UI. If the |
Manual approval of component requirement required |
| PPF or Background | This alert is relevant for purchase order collaboration with approval process. The customer must accept the component requirement that the supplier has confirmed manually on the purchase order collaboration Web UI. If the |
Confirmation rejected |
| PPF or Background | This alert is relevant for purchase order collaboration with approval process. The customer has rejected the confirmation schedule line manually on the purchase order collaboration Web UI. If the |
Component requirement rejected |
| PPF or Background | This alert is relevant for purchase order collaboration with approval process. The customer has rejected the component requirement that the supplier has confirmed manually on the purchase order collaboration Web UI. If the |
New note for purchase order |
| PPF or Background | The customer or supplier has created a new note for a purchase order or a purchase order confirmation in purchase order collaboration. If the |
Purchase order overdue |
| Report | The purchase order contains due schedule lines with an ASN-based due quantity in the past. The schedule lines, therefore, are not fully covered by ASNs. System administration generates these alerts with the |
Purchase order due within lead time |
| Report | The purchase order contains schedule lines in the future that lie within the lead time and that are not fully covered by ASNs. System administration generates these alerts with the |
New attachment added to purchase order |
| Automatically | A new attachment has been added to the purchase order, using the attachment handling functionality of SAP SNC (without Collaboration Folders). |
The ID
column contains the alert type ID. The Source