Source Determination in PP/DS
If you want
to create a procurement proposal in Production Planning and Detailed
Scheduling (PP/DS), a
source of supply has to be determined for the procurement
proposal.
In most
applications, this takes place using the
source
determination function.

An exception is the creation of PP/DS procurement proposals from ATP tree structures. In this case, the source of supply is specified by Global ATP. When PP/DS procurement proposals are generated from Supply Network Planning (SNP) procurement proposals, PP/DS can adopt the sources of supply that source determination has determined for the SNP procurement proposals. PP/DS does this instead of using automatic source determination to redetermine PP/DS sources of supply. For more information, see Converting ATP Tree Structures and Conversion of SNP and CTM Orders into PP/DS Orders.
The following table gives an overview of the application-specific characteristics of automatic and interactive source determination in different PP/DS applications.
Application |
Description |
· Action Cover Dependent Requirements Immediately · Product heuristic: Planning standard lots (SAP_PP_002) · Product heuristic: Planning shortage quantities (SAP_PP_003) |
These PP/DS
applications determine sources of supply automatically. Automatic
source determination takes
account of the procurement type from the location product master and thus all
sources of supply that correspond to the procurement type.
The planning
application selects the (quota-allocated) source of supply with the highest
priority and the lowest costs with which the requirements date/time can still
be adhered to. The application selects this source from the
|
Product heuristic: Least-unit cost procedure: external procurement |
This heuristic tries to find optimum order quantities, while taking storage costs and procurement costs into consideration. Automatic source determination only considers sources of supply for external procurement here, irrespective of the procurement type in the location product master. Storage costs and procurement costs are decisive factors here in source of supply selection. |
Interactive creation of receipts |
If several
valid sources of supply exist, source determination is performed
interactively. The system
shows the ranking list of the valid, alternative sources of supply and you
make a manual selection according to your own criteria.
For more
information, see
|
To prioritize sources of supply, source determination uses the following costs from the sources:
· Sources of Supply for In-House Production
In the case of a production process model, the system calculates the production costs from the fixed and variable (that is, quantity-dependent) costs, which you have entered in the production process model plan under multilevel costs. The costs are 0 for iPPE access objects and runtime objects.
· Sources of Supply for External Procurement
In the case of an external procurement relationship, the system uses the procurement costs function of the external procurement relationship; these costs are transferred automatically from SAP R/3 to the external procurement relationship. In the case of a transportation lane or an external procurement relationship without a procurement costs function, the system uses cost data that you have specified manually in the transportation lane. You can specify blanket, quantity-independent product procurement costs or a cost function. The system uses the cost function, or, if no cost function exists, the product procurement costs.
In the planning version, you can define for PP/DS whether the system may create a procurement proposal if no valid sources of supply are available. If you allow procurement proposals without valid sources of supply, the system creates the following procurement proposals:
· A purchase requisition without a source of supply, in the case of an externally-procured product
The system schedules the purchase requisition, while taking account of the goods receipt processing time and the planned delivery time.
· A planned order without source of supply, in the case of a product produced in-house. This also applies if a product can be both produced in-house and procured externally.
The duration of the planned order is 0. It only contains a receipt but no activities or dependent requirements. The system schedules it for the desired availability date/time.
In the order processing view, you can change the source of supply of a procurement proposal. In particular, you can change a purchase requisition with reference to a source of supply into a purchase requisition without a source of supply.
·
Planning and Source
Determination in External Procurement