Start of Content Area

Function documentation Mass Transfer and Mass Conversion of Orders  Locate the document in its SAP Library structure

Use

You can use this function at any time in SAP APO to transfer planned orders or purchase requisitions, whose opening dates are in the past

Using the conversion checks, you can exclude orders from the transfer, if they do not fulfill specific business prerequisites.

Prerequisites

See Converting purchase requisitions

Features

Determining the opening date

With mass transfer and mass conversion, you can transfer or convert a planned order or purchase requisition only if the opening date is today’s date, or if the opening date has passed (that is, is in the past). The system calculates the opening date for an order as follows, using the opening period that you have specified in the location product master for the order product.

Order

Opening date

Production order

Production start date - opening period

Purchase order

Delivery date - planned delivery date - opening period

The system uses the planned delivery time from the external procurement relationship.

If necessary, you can extend the opening period for transfer or conversion by the required number of calendar days.

Selection criteria

You can select the orders that you want to display, transfer or convert, according to various criteria. For example, you can select orders with the following characteristics:

Execution options

You can

To do this you can specifically transfer only those orders that have not yet been transferred into the SAP R/3 system.

For this option, the system sets the conversion indicator for the selected orders (if the conversion check permits), and only transfers the orders for which the conversion indicator has been set.

For more information, see Executing mass transfer or mass conversion

Transfer time

When executing the option transfer or convert, the SAP APO system does not necessarily transfer the orders immediately to the SAP R/3 system; the SAP APO system only creates transfer events for the selected orders. The actual transfer time depends on the settings you have made for the transfer. You have the following options:

For more information, see Transferring orders to the SAP R/3 system

Activities

You call up mass transfer or mass conversion in the area menu for Production Planning under Manufacturing execution Conversion of orders/purchase requisitions.

 

 

End of Content Area