You use this procedure to run a report that informs you of the daily duration and start delays of SAP BW process chains. The system gets the job data from business process monitoring.
You use business process monitoring and have activated job monitoring for process chains.
You have fulfilled the prerequisites for SAP BW reports in job scheduling management. For more information, see Job Scheduling Management Health Check Reports.
In the Job Management
work center, choose .
In the table of reports, navigate to the row for the process chain-specific weekly view in business process management.
In the detail area below the table, the system displays further information, such as the template ID
.
Choose Report
.
A dialog box appears.
Note
You can also execute the report within the open report dialog. In this case, enter the variable selection criteria on the Preview
tab.
Enter a solution name.
The system selects all jobs that ran for this solution.
To further restrict the search results, you must specify the calendar week.
Choose Execute
.
The system opens a report with the evaluation results. The report contains the selection criteria, the selected processes and process steps as well as the following information in table and graphic form:
Maximum duration of the process chain per day
Maximum start delay of the process chain per day