You want to release the transport requests that are part of your changes from the Solution Manager system.
A task list exists with the status Active
.
You have been assigned the SAP_CM_DEVELOPER_COMP
role in the SAP Solution Manager system.
Note
If you want to release transport requests from within the administration cockpit, you must have the SAP_CHANGEMAN_OPERATOR
role in the managed system.
To release a transport request from within a change document, go to the Transport Management
assignment block and proceed as follows:
Urgent changes that are in status “In development”: Select the transport request and choose Release Transport Request
.
Transport requests of urgent changes can also be released automatically when the status is set to “To be tested”.
Normal changes: Transport requests are automatically released when the change document is set to “Successfully tested”.
To release a transport request from within a task list, proceed as follows:
In the administration cockpit, choose Task Lists
.
Choose the relevant change cycle.
Click the task list for which you need to release transport requests.
Under the task node of the development system, select Release Transport Request
and start the action by clicking Execute
. You can then decide whether you want to execute the task immediately or at a scheduled time.
In the dialog box that appears, select the transport request(s) that you want to release.
Note
The following open transport requests are displayed:
From within a change document: all requests that are assigned to the change document
From within a continual cycle task list: all requests that are assigned to the CTS project connected to the cycle
From within an urgent change task list: all requests that are assigned to the urgent change
After the transport requests have been released, the task list is displayed again.
Check the status of your task. If you need more information about the task, check the application log in the Daily overview
of the task list.
In the selected development system, the transport requests that you specified have been released (provided that they do not contain any open tasks).
Note
If there are empty transport requests that meet the criteria in step 5, they are deleted.