Function documentationMaintenance Cycles in QGM

 

The lifecycle of a maintenance project is divided into maintenance cycles (MC). When a maintenance cycle comes to an end, you can start a new maintenance cycle and continue to use the maintenance project for further software changes.

Features

All software corrections must be tested and implemented within one maintenance cycle. At the end of the maintenance cycle, corrections are imported into the production system. Open changes, open transport requests, and transport requests that have not been imported to production systems are moved to the new maintenance cycle. The switch from an old maintenance cycle to a new one is safeguarded by the Deploy to Scope quality gate.