Function documentationEditing Test Plan Attributes

 

You want to display or change attributes in the test plan of a project.

Example Example

You want to change the release status, the planned start and end date, or the person responsible for the test plan.

End of the example.

Prerequisites

  • You have the authorization to change test plans.

  • In the Test Management work center, under Test Plan Management, you have selected the Test Plans view.

Features

The scope of attributes you can edit depends on whether you edit single or multiple test plans.

For multiple test plans, you can edit a limited range of attributes, for example, the system role or the person responsible, but not the test effort or attachments.

For a single test plan, you can edit the attributes, which you specified when you created it (except for, for example, Template Projects), in the following tabs:

Tab

Function

General Data

You can, for example, change the test plan release status.

Caution Caution

If you change the system role of a test plan, this can lead to inconsistencies in the test results, if the test plan has already been processed, because you now access test cases in other systems. Only change the system role if it will not cause inconsistencies.

End of the caution.

Default values

You can, for example, specify the documentation type for test notes.

Planned data

You can specify whether, and at which level, to manage the expected test effort, and display or specify the expected test effort values. The system shows the actual effort (the actual effort expended by testers) automatically. For more information, see Plan Test Times and Effort.

Automatic Test

You choose, for example, a system data container, which determines the systems in which the automatic tests are to be performed. See Using System Data Containers.

Note Note

If you use test cases of type referring, you must specify the target system in which the test cases referred to were specified, in the Automatic Test tab.

End of the note.

History

You can display an overview of the changes made so far to the test plan.

Attachments

You can attach documents which are relevant for test planning and execution, e.g. EXCEL tables of test data, to the test plan.

Administration data

You can display who created and last changed the test plan, and the associated times.

Business Process Change Analyzer

If a test plan was created with BPCA, you can display its results ID. See Business Process Change Analyzer.

Activities

Changing a single test plan
  1. Select the test plan and choose Start of the navigation path Change Attributes Next navigation step Change Single Test Plan End of the navigation path.

    You go Test Plan Attributes screen.

  2. Change the relevant attributes on the tab pages, for example, on the Planning Data tab page, the test effort.

  3. Save your entries.

Changing multiple test plans
  1. Select the test plans, and choose Start of the navigation path Change Attributes Next navigation step Change Multiple Test Plan End of the navigation path.

    You go to the Mass Changes: Test Plan Attributes screen.

  2. Change the relevant attributes in the columns, e.g. Person Responsible.

  3. Choose the Apply Mass Change pushbutton.

  4. Save your entries.