You download the project structure or a roadmap into MS Project to plan your project using the data in the project structure or roadmap.
MS Project is installed on your local computer.
You have created a project structure in the Business Blueprint phase or called a roadmap. You are in the
Business Blueprint
transaction or the structure view of a roadmap.
Caution
You have created at least one structure element with data, at the lowest level, under each structure element in the Business Blueprint, so that the data is displayed correctly in MS Project.
If you are in the
Business Blueprint
transaction, choose
If you are in the structure view of a roadmap, choose
Choose a folder for the file, in the following dialog box, and change the file name if required.
Save.
Confirm the following system message with
Continue
.
The project structure or the roadmap is generated as an .mpx file and displayed in MS Project. You can now save the file in .mpp format and edit it.
Make the following settings in MS Project, so that it displays all required fields after you have downloaded a roadmap or a project structure:
Define a user display table with
.Create one or more of the following fields for the display table, as required:
Field |
Meaning |
---|---|
Unique ID |
Sequential number in MS Project |
Text1 |
SAP GUID of structure element |
Name |
Name of structure element |
Outline Level |
Outline level of structure element |
Priority |
Priority of structure element |
Milestone |
Milestone flag in the Roadmap |
Text2 |
Status of structure element |
% Complete |
|
Planned Start |
|
Planned Finish |
|
Planned Duration |
|
Actual Start |
|
Actual Finish |
|
Actual Duration |
|
Remaining Duration |
|
Resource Names |
Project Team Members |
Resource ID |
Project team member – SAP user name |
Resource name |
Project team member – Name/Description |