You can run CATT test cases in a test package in the background. This can make testing more efficient. You can e.g. specify the execution timeout period for test cases. The execution of test cases can be conditional. The performance of the test package can depend on the result of another program. This new function is realized in the Computing Center Management System (CCMS). See Background processing.
A test package has been created.
...
1. Choose the Tools → ABAP Workbench → Test → Test Workbench → Test Organizer → Test Plan Management menu.
2. Choose a test plan.
3. Choose the Test Packages pushbutton.
4. Choose a test package.
¡ Choose the Goto → Run CATT in Background menu.
You go to the Computing Center Management System (CCMS).
5. If necessary, make the print settings.
6. When you save the print settings, you go to the Start times screen.
7. Choose your options for running test packages in the background.
See also: System Management.
You have created logs by running test cases in the background.
When the test package runs, a field with the test plan log procedure number is created. The log is accessed with this procedure number.
...
¡ Choose Goto → Select Log → CATT.
1. Enter the procedure number.
2. Choose Execute.
You can cancel the setting to run test packages in the background in the Computing Center Management System (CCMS).