You are on the initial screen of
Project Administration
.
Select the project you want to copy.
.
Specify a name for the target project.
Note
You can use the input help to view the project names that have already been entered in your SAP Solution Manager system.
Check the project type if necessary.
Enter a project name.
Choose which data of the project you want to copy:
Header Data, for example
Project Team Member
or
System Landscape
.
Activity Data, for example
Status,
Plan Data
or
Actual Data
.
Documents
Roadmap Data, for example
Roadmap Assignments,
Status
or
Notes
.
Test Plans
Business Function Scope
Technical Bill of Material
If you want to copy project data, select the relevant indicator.
If you do not want to copy project data, deselect the relevant indicator.
Choose
Execute
.
The system copies the project.