Show TOC

Procedure documentationRerecording TBOM Recording Work Items Locate this document in the navigation structure

Prerequisites

You are entered as a quality expert in a TBOM recording work item.

The TBOM recording work item has the status Query Back to QA Expert or Completed.

Procedure

  1. In the Test Management work center, choose the TBOM Worklist view.

  2. For the role Quality Expert, choose the query My Tasks.

  3. Select the work item that you want to record again and choose Change.

  4. Change the work item status to one of the following values:

    • TBOM Initial Recording

    • TBOM for Enhancement

    • TBOM New Recording

  5. Save the work item.

Result

In the standard configuration, the system notifies the business process expert responsible about the new work item by e-mail. The work item appears in the TBOM worklist of the business process expert.