Start of Content Area

Procedure documentation Copying Projects  Locate the document in its SAP Library structure

Prerequisites

You are on the initial screen of Project Administration.

Procedure

...

       1.      Select the project you want to copy.

       2.      Choose Project Copy.

       3.      Specify a name for the target project.

Note

You can use the input help to view the project names that have already been entered in your SAP Solution Manager system.

       4.      Check the project type if necessary.

       5.      Enter a project name.

       6.      If you do not want to copy project data, project documentation, test cases, or the defined scope of assigned business functions to the new project, deselect the relevant indicator. By default, all values are selected.

       7.      Choose Execute.

The system copies the project.

 

End of Content Area