Using Test Management 
You can assign test plans and test packages to change requests and change documents and thereby document and track the corresponding tests as well as navigate directly to execution. You assign test plans and test packages in the Test Management assignment block. The assignment block must be in change mode.
Assignment of test plans and test packages from the Test Workbench
If you have already assigned a project or solution, the system displays only the test plans and test packages that belong to the respective project or solution. If you have not yet made an assignment, you can only assign test packages.
You can add new assignments and change existing ones as long as the test for the change document has not yet begun, that is, as long as the status allows it.
Navigation to test execution in the tester worklist
Display of test status in the status info system for test plans and test packages
To display the status info system and the test report, select a line with a test plan or test package and choose the desired function.