Show TOC

Procedure documentationDecoupling a Transport Request Locate this document in the navigation structure

 

You can decouple changeable transport requests from change documents.

Example Example

A development in a normal change is not finished, and is to be moved, because the change cycle is to finish. To separate these developments from your change document and finalize the other parts of your project, you can decouple the transport requests with the unwanted changes.

End of the example.

Procedure

  1. Select a transport request in the Transport Management assignment block.

  2. Choose   More   Decople Transport Request  .

  3. Confirm that you want to decouple the transport request, in the dialog box.

Result

The transport requests are decoupled from your change document, and are no longer displayed in the Transport Management assignment block. When you transport the changes in this change document into your production system, the decoupled request is not transported. You can assign it to another change document, with the function Assign Transport Request.

More Information

Assign Transport Requests