  Rough Workload Estimate

Use

This function provides you with an overview of the estimated transportation workload for a relocation or relocation step at any early stage in the planning process.

Integration

For more information, see Assignments for Relocation (Infotypes 1981/1982) .

Features

Weight and volume data is determined as follows:

  • Material

    • Authorized Material

      If material has not been planned in detail, a model assigned to the respective material planning object (MPO) is used as a calculation base for stock. If material has been planned in detail, the respective material master record is used.

    • Logistical Reqmts

      The material master data stored for the corresponding logistical requirements is used for provisions.

  • Personnel

    To calculate personnel, the weight groups of the assigned positions as well as the number of assigned persons are used.

The following fields are available for a force element in the Structures Workbench on the Rough Workload Est. tab page:

  • Rough workload estimate for material (top screen area)

    • Relocation Step ID/Object Name

      The relocation step included in the rough workload estimate.

    • Issuing Force Element/Object Name

      The issuing force element.

    • Receiving Force Element/Object Name

      The receiving force element.

    • Organizational Area

      The organizational area of the issuing force element.

    • Iss.Plnt / Iss. SLoc / Rcvg Plnt / Rcvg StorLoc.

      The issuing and receiving plants and storage locations.

    • Delivery Date

      The date on which the goods ordered during the conversion process are to be delivered.

    • Material/MPO and Material/MPO - Description

      The object ID and description of the assigned material master record or MPO.

    • Icon Stock/Provs and ID Stocks/Provs

      Specifies whether an entry refers to stock or provisions.

    • Σ Planned Quantity

      The number/quantity specified for the assignment of the material to the relocation step.

    • The numerous properties from the underlying material master record. For example:

      • Base Unit of Measure

      • Σ Net Weight in KG

      • Σ Gross Weight in KG

      • Σ Volume in m³

      • Material Group Packaging Material

      • Transportation Group

      • Loading Group

      • Material Group

      • External Material Group

      • Dangerous Goods Indicator Profile

      • Military Goods

  • Rough workload estimate for personnel (bottom screen area)

    • Relocation Step ID/Object Name

      The relocation step included in the rough workload estimate.

    • Object ID/Object Name

      The receiving force element.

    • Organizational Area

      The organizational area of the force element.

    • Position Object ID/Object Name

      The assigned position.

    • Weight Group

      The weight group of the assigned position.

    • Number of Passengers

      The number of assigned persons.

    • Σ Quantity

      The weight of the weight group.

    • Base Unit of Measure

      The base unit of measure of the weight group.

  • In the last row in each screen area, the totals are displayed.

    Note Note

    To show and hide fields, you can choose Layout Settings…

    The type of relocation step determines whether data for both the issuing and receiving force element exists for the rough workload estimate, and therefore which material master data is available in this estimate. In accordance with the Customizing settings in the standard system, only data for the receiving force element is available for type 1, and for types 2 and 3, the data for the issuing force element is the same as that for the receiving force element.

    End of the note.

Activities

To create a rough workload estimate, choose one of the following from the selection area in the Structures Workbench :

  • A relocation, to display a rough workload estimate for all of the relocation steps in a relocation

  • A relocation step, to display a rough workload estimate for an individual relocation step