Definition

A material planning object (MPO) that is assigned to a different MPO.

Use

Additional parts represent equipment that is managed individually as MPOs for planning reasons but that is needed to run the equipment to which it belongs and is therefore assigned to the relevant MPO.

Structure

Technically, the assignment of MPOs to MPOs as additional parts is implemented by an iPPE relationship of type S_DFBOM.

You create the properties of the MPO to MPO assignment as an additional part on the Additional Parts tab page of the higher-level material planning object .

  • MPO

    The unique object ID of the MPO assigned as an additional part.

  • Description

    The long name of the MPO assigned as an additional part.

  • Quantity

    The planned quantity of the MPO assigned as an additional part.

  • Assignment Indicator

    Specifies whether the additional part is a mandatory or an optional part.

    • Mandatory Part

      The additional part is a mandatory part.

    • Optional Part

      The additional part is an optional part and a separate decision must be made about each assignment depending on the type of operation or the task in question.

    • No Special Identification

      The additional part is an optional part and the system informs you of available scheduling for this additional part to enable you to make a decision regarding further scheduling.

Storage

Assignments of MPOs as additional parts are stored in the following tables:

Additional parts

Table

Data

/ISDFPS/PRMPOID

iPPE Relationship: Time-Independent ID and Attributes

/ISDFPS/PRMPO

Attributes of BOM Relationships

Integration

If you assign a force element or material container an MPO that is assigned to additional parts, you can decide whether to also assign these additional parts to the higher-level object.

  • By choosing Start of the navigation path Organizational Flexibility Next navigation step Assignments Next navigation step Define Settings for Assignments End of the navigation path in Customizing for Defense Forces & Public Security , you can set the ASSIGN_OP_PARTS switch to specify whether you want to assign dependent additional parts and select one of the corresponding two user dialogs to be available:

    • Automatic dialog

      When you assign a material planning object with additional parts to a force element or material container, the system automatically displays a dialog box in which the user can decide whether to assign dependent additional parts.

    • Assign Additional Parts pushbutton

      This pushbutton is provided on the tab pages for assigning MPOs to force elements or material containers so that you can assign dependent additional parts for MPOs already assigned.

  • In Customizing for Defense Forces & Public Security , you can define whether mandatory parts, optional parts, and parts without any special identification are to be preselected for the assignment and whether the selection can be changed during detailed planning, by choosing Start of the navigation path Organizational Flexibility Next navigation step Assignments Next navigation step Control Assignment of Additional Parts End of the navigation path .