Material Planning Object View A group of several material planning objects (MPOs) as a hierarchical structure for viewing purposes
You can use the MPO view to group MPOs for viewing purposes. From a procedural perspective, the view node is a project-related product structure.
Example
For example, if a new product is specified, developed, or procured, all the MPOs that are part of the project are grouped below this node.
In contrast to the material container, the MPO view is not used in material planning and material management processes.
Technically, the MPO view is implemented as an iPPE node of type S_DFMPOV.
You can make the following assignments on the tab pages in the application
Authorized Materials and Material Packages
:
Downwards Relationship
tab page
On this tab page, you create bundles of several MPOs.
Upwards Relationship
tab page
On this tab page, you can define relationships to other view nodes.
An MPO view comprises several MPOs and can be assigned to other view nodes.