Report: Scheduled Material Planning Objects You use this report to check whether the upper limits defined for the assignments of material planning objects (MPOs) to force element are observed in each organizational area.
You have defined upper limits for the MPOs that you want to evaluate.
The following selection and evaluation parameters are available in the application
Scheduled Material Planning Objects
:
Material Planning Object
In this section, you specify which MPOs you want to evaluate. If necessary, limit the selection using the
Material Indicator
,
Key Date
, and
Usage Type
properties
.
If necessary, specify whether you also want to evaluate MPOs that are assigned to a force element by means of a material container.
Status of Assignment
In this section, you specify which assignment statuses you want to evaluate.
Force Element
In this section, you specify which force elements you want to include in the report.
Start the application
Scheduled Material Planning Objects
(transaction /ISDPFS/MPO_PLAN).
Enter the required selection and evaluation parameters.
Execute the report.
All determined assignments are displayed in the result list. The upper limits are displayed in the
No.of Org.Areas
field.