 Report: Scheduled Material Planning Objects

Use

You use this report to check whether the upper limits defined for the assignments of material planning objects (MPOs) to force element are observed in each organizational area.

Prerequisites

You have defined upper limits for the MPOs that you want to evaluate.

Features

The following selection and evaluation parameters are available in the application Scheduled Material Planning Objects :

  • Material Planning Object

    In this section, you specify which MPOs you want to evaluate. If necessary, limit the selection using the Material Indicator , Key Date , and Usage Type properties .

    If necessary, specify whether you also want to evaluate MPOs that are assigned to a force element by means of a material container.

  • Status of Assignment

    In this section, you specify which assignment statuses you want to evaluate.

  • Force Element

    In this section, you specify which force elements you want to include in the report.

Activities

  1. Start the application Scheduled Material Planning Objects (transaction /ISDPFS/MPO_PLAN).

  2. Enter the required selection and evaluation parameters.

  3. Execute the report.

    All determined assignments are displayed in the result list. The upper limits are displayed in the No.of Org.Areas field.