Show TOC

 Copying Standard SOP Results for a Material

Procedure

  1. Select SOP results for material in the dialog box and choose Continue .

  2. Define the reference and choose Continue.

  3. Define the transfer strategy and choose Continue .

  4. You can change the reference in Change reference values by changing the following parameters and choosing Continue .

  5. – Planned quantity

    – Postpone

    – Percentage

    Display references appears. You can check the reference quantity.

  6. Select the product group member, and choose Choose .

  7. The system copies the reference for the current material. You can check and change the quantities and dates.

  8. Select the item, and select Schedule lines .

Result

On the schedule lines screen, you can check and change the quantities and dates.

See also: