Show TOC

 Copying Standard SOP Results for a Product Group

Procedure

  1. Select SOP results for product group in the dialog box and choose Continue .

  2. Define the reference and choose Continue.

  3. Define the transfer strategy and choose Continue .

  4. Select the product group members, and choose Continue.

  5. The reference quantities are copied to the item screen.

  6. Select the item, and select Schedule lines .

Result

On the schedule lines screen, you can check and change the quantities and dates.

See also

Changing PIRs