MTO Production for Material Variants (26)This strategy is similar to Make-to-Order Production (20) . The difference is that strategy 26 lets you change the configuration of the variant.
You must maintain the following master data settings:
One configurable material with the standard configuration data such as characteristics, classes, and configuration profiles.
One variant for defined combinations of characteristics values. Limit the number of combinations.
Stage 1: Demand Management
Does not apply.
Stage 2: Procurement Before Sales
Does not apply.
Stage 3: Sales Order
You create a sales order either directly by entering a variant or a configurable material and using variant determination. The system finds the requirement type
KEL
because the strategy group has been set to
26
. To display the requirement type from the Sales Order screen, choose
Procurement
tab strip.
Stage 4: Procurement After Sales
Make-to-Order production of the finished product takes place.
Stage 5: Goods Issue for Delivery and Reduction of Planned Independent Requirements
Delivery of the finished product takes place.
See also