If you do not want to manually create the production process model for a product in SAP APO, but want to create it by transferring it from SAP R/3 to SAP APO, you must define a production version for the product in SAP R/3.
Note
Like the production process model, the production version links BOMs and routings (material lists and recipes for the process industry).
Choose
Production versions
on the
MRP 4
tab page of the SAP R/3 material master.
Enter the version number, description, and validity period and then choose
Details
.
For detailed scheduling, enter the following planning data:
Planning type
: N (for normal routing)
Planning group
: Routing number