 Standard Planning Procedure 4

Use

For this planning procedure, the system creates a planning file entry for all planning-relevant changes for a location product. You can plan the product in the production planning run using net change planning with a suitable heuristic. Planning with heuristics allows you to use any lot size procedure. For net change planning in the production planning run, the heuristic only plans products that have a planning file entry.

Note Note

For net change planning, you can use one of the following heuristics that plan according to MRP logic. These heuristics execute the product heuristics set for each product in the product master.

End of the note.
  • SAP_MRP_001: Product planning (components according to low-level code)

  • SAP_MRP_002: Product planning (plan components immediately)

For more information on these heuristics, see Heuristics for Production Planning .