 Net Requirements Calculation (Heuristic SAP_PP_SL001)

Use

If a heuristic for planning standard lots (for example, the standard heuristic SAP_PP_002 or SAP_PP_SL001) should consider the shelf life conditions during planning, the standard net requirements calculation only offsets stocks, receipts and requirements with compatible shelf life data.

Prerequisites

You should not have set the consider fixed receipts first indicator in the heuristic settings. The net requirements calculation must therefore use the minimize alerts procedure.

Features

So that the net requirements calculation can offset a stock or receipt element with a requirements element, the elements must fulfill the following shelf life conditions:

  • The stock or receipt element must have completed the maturation time by the requirements date

  • The stock or receipt element must keep until at least the required minimum shelf life of the requirements element

  • The stock or receipt element may keep at most until the required maximum shelf life of the requirements element

Firmed receipt elements for which the heuristic does not find any suitable uncovered requirements create a surplus. The Alert Monitor can display alerts for surpluses with limited shelf life. The heuristic creates procurement proposals for the uncovered requirements in the further planning process.