You can use the new multi-resource scheduling heuristic (SAP_MULT_SCH
) to switch modes and sources of supply according to defined time blocks, so as to keep the receipts as close to the required date as possible.
Multi-resource scheduling provides the following advantages:
Complies better with due dates
Supports finite production planning scenarios with all alternative resources
Allows alternative resources to be modeled using not only modes but also alternative sources of supply
Note
This heuristic does not schedule process orders. It considers only planned orders for scheduling, subject to their fulfilling all other prerequisites.
The following master data has been maintained:
Location
Products
Resources
PPM/PDS (Alternative PDS should have different resources)
Multiple orders for the finished product on the same day
The heuristic has been added to the heuristic profile to be accessible from the Detailed Scheduling Planning Board
. In Customizing, go to .
You have activated the business function SCM-APO-PPS, Continuous Production and Multi-Resource Scheduling (SCM_APO_PPDS_PI
).
Run transaction /SAPAPO/CDPS0
for the Detailed Scheduling Planning Board
.
Select the overall profile SAP001
and planning version 000
.
Enter the resource, location, or product in which the orders exist. Choose Execute
.
Choose Profiles
and select the heuristic profile defined in Customizing. Then choose Copy (Enter)
to save the setting.
Select a resource with the orders.
Choose
to run the heuristic.The orders are scheduled in alternative modes, and different sources of supply are chosen after the switch over time.