 Stable Forward Scheduling

Use

You can use this heuristic to carry out multilevel finite scheduling in the detailed scheduling planning board and in the production planning run , in order to create a feasible short-term production schedule.

This heuristic uses the algorithm /SAPAPO/SFW_HEUR_FW_STABLE.

You use stable forward scheduling to resolve the following planning problems, across a number of production steps:

  • Backlog

  • Capacity overload

  • Violation of minimum intervals

  • Violation of validity intervals of orders

For more information about prerequisites and activities for using the detailed scheduling heuristics, see Detailed Scheduling Heuristics .