Integrated processing of stock transfers using SAP APO and one or more SAP R/3 systems is possible in the following processes:
Stock transfer
Cross-system stock transfer
This scenario is only supported as of SAP R/3 Enterprise. For more information, see the information for SAP R/3 Enterprise under
.Cross-System Stock Transfer Using Purchase Order and Sales Order
Stock transfer of consignment stock
System-internal stock transfer (Consignment) using stock transport requisition
This scenario is only supported as of SAP R/3 Enterprise.
Cross-system stock transfer (consignment)
This scenario is only supported as of SAP R/3 Enterprise. For more information, see the information for SAP R/3 Enterprise under
.Cross-system stock transfer (consignment) using purchase order and consignment fill-up
For more information, see the documentation for SAP R/3 under
.Subcontracting
In SAP APO 3.1, this scenario is only supported by Production Planning and Detailed Scheduling (PP/DS) and not Supply Network Planning (SNP). For more information, see Subcontracting
Stock transfer using stock transport scheduling agreement
This scenario is supported by both PP/DS and SNP. For more information, see Procurement Scheduling Agreement and Procurement Scheduling Agreements in Heuristics-Based SNP Planning .
Stock transfer using stock transfer reservation
For more information, see the documentation for SAP R/3 under
.