 Possible Combinations for Production

Possible settings in the check instructions for calling PP/DS

Type of inspection method:

  • P = Product availability check

  • A= Product allocation

  • C = Checking against forecast

Setting for calling PP/DS:

  • Sequence = Sequence of check methods

  • Time of production

    • Inspection methods = After executing all inspection methods

    • Product availability check = After executing the product availability check

The system behaves as follows:

Requested quantity is 100 PC.

Sequence

Time of production

Production

Confirmed quantity

  1. P (25)

  2. A (45)

Check methods

75

100

  1. P (25)

  2. A (45)

Product availability check

75

45

  1. P (65)

  2. A (20)

Check methods

80

100

  1. P (65)

  2. A (20)

Product availability check

35

20

  1. A (45)

  2. P (25)

  3. C ( 10 )

Check methods

75 ( 90 )

100 ( 100 )

  1. A (45)

  2. P (25)

  3. C ( 10 )

Product availability check

20

45 ( 10 )

  1. A (20)

  2. P (65)

Check methods

80

100

  1. A (20)

  2. P (65)

Product availability check

0

20

  1. A (65)

  2. P (25)

  3. C (10)

Check methods

90

100

  1. A (65)

  2. C (10)

  3. P (25)

Product availability check

40

10

  1. A (65)

  2. C (10)

  3. P (25)

0

10

Note Note

In production according to the inspection method product availability check , the system can attempt to create a planned order that can only be partly or not at all taken into account in the final result because of the results of other inspection methods.

For the multi-level ATP check, the order quantity is adjusted in the tree at the end of the ATP check. For Capable-To-Promise, the planned order is only adjusted when the function Automatic Planning When Saving a Sales Order is triggered while saving the sales order.

End of the note.