Possible Combinations for Production Possible settings in the check instructions for calling PP/DS
Type of inspection method:
P = Product availability check
A= Product allocation
C = Checking against forecast
Setting for calling PP/DS:
Sequence = Sequence of check methods
Time of production
Inspection methods = After executing all inspection methods
Product availability check = After executing the product availability check
The system behaves as follows:
Requested quantity is 100 PC.
Sequence |
Time of production |
Production |
Confirmed quantity |
|---|---|---|---|
|
Check methods |
75 |
100 |
|
Product availability check |
75 |
45 |
|
Check methods |
80 |
100 |
|
Product availability check |
35 |
20 |
|
Check methods |
75 ( 90 ) |
100 ( 100 ) |
|
Product availability check |
20 |
45 ( 10 ) |
|
Check methods |
80 |
100 |
|
Product availability check |
0 |
20 |
|
Check methods |
90 |
100 |
|
Product availability check |
40 |
10 |
|
0 |
10 |
Note
In production according to the inspection method
product availability check
, the system can attempt to create a planned order that can only be partly or not at all taken into account in the final result because of the results of other inspection methods.
For the multi-level ATP check, the order quantity is adjusted in the tree at the end of the ATP check. For Capable-To-Promise, the planned order is only adjusted when the function
Automatic Planning When Saving a Sales Order
is triggered while saving the sales order.