Before the system can reschedule the activities, the heuristic arranges them in a certain sequence. The following sort criteria are used:
Requirement date
ATP category (in accordance with special sorting)
Confirmed/unconfirmed sales order
Order priority
Setup sequence
The following sort criteria are also bequeathed to the subordinate BOM levels with the aid of fixed pegging:
ATP category
Confirmed/unconfirmed
Order priority
This independent requirement information is also passed on to the subordinate orders of the pegging structure via the pegging. If an order is linked to more than one superordinate order via pegging, it inherits the information with the highest priority in each case. This is shown in the following graphic:
The graphic shows how the information relating to independent requirement E (sales order) is passed on to the order A. First the
ATP category
is considered. Because the
category BM
(sales order) is rated as more important than
category FA
according to the sort profile, the system passes on the
category BM
to the orders B and A. After this, the information
confirmed
or
not confirmed
is passed on. Since order A is linked to orders B and C via pegging, order A inherits the information confirmed by order C, because a confirmed sales order has a higher priority than an unconfirmed one. Lastly, the order priority is passed on.
You have specified the ranking order for the individual sort criteria in Customizing for PP/DS under
. You have checked the ranking order of the
ATP categories
in
Special Sorting
in Customizing.
In the following example, sorting according to the sort criterion
requirement date
is shown. In this example, further sorting with the sort criterion ATP category is superfluous, because the system can create a unique sequence based on the requirement date.
The system is to sort the following four operations/orders:
Order no. |
Requirement date/time |
Independent requirement information |
---|---|---|
P1 |
20.04.2005 |
Sales order (BM) |
P2 |
20.04.2005 |
Planned independent requirement (FC) |
P3 |
27.04.2005 |
Sales order (BM) |
P4 |
26.04.2005 |
Planned independent requirement (FC) |
P5 |
21.04.2005 |
Planned independent requirement (FC) |
The system determines the following sequence for scheduling based on the requirement date/time:
P2
P3
P4
P1