The following evaluations, which you can also call up in the area menu of
Reporting
and in the
detailed scheduling planning board
, are available for resources, orders, and products in
Production Planning
:
Evaluation |
Description |
---|---|
Resource load |
Displays the resource load per period or per block for selected single or multi-resources |
Work-in-Process stocks |
Displays the Work-in-Process stocks for operations on selected resources, that is, the quantity of unprocessed material awaiting further processing in these operations For more information, see Evaluations for Work-in-Process Stocks . |
Operation list |
Displays a list of operations for selected resources that are processed on these resources |
Order list |
Displays a list of orders for selected resources that are processed on these resources |
Production overview |
Displays a production overview for selected products In the production overview, the quantities and status of products are listed; for example, which quantity of a product has been released or confirmed. |
Capacity reservation |
Displays an aggregated view of capacity reservation data. You can view:
|
Note
You can call up a list with production-relevant data for activities on selected resources and
lines
in the area menu of
Reporting
under
Production list
.
An evaluation refers to a certain evaluation period and a certain planning versionor simulation version:
When you call up the evaluation function in the detailed scheduling planning board, the system creates the evaluation for the current display period and simulation version in the detailed scheduling planning board.
You must specify a planning version and an evaluation period if you call up an evaluation in the
Reporting
area menu.
Using the customer exit APOCSPS5, you can enhance the evaluations with user-defined columns and enter values in these columns. The system automatically enters values when you call up the evaluation. For more information, see the system documentation for the customer exit.
You call up the evaluations
in the
Reporting
area menu under
Order and Resource Reporting
in the detailed scheduling planning board under