In addition to the
heuristics
and
optimization
, the following standard functions, which you can use to define the resource schedule and the object selection, are also available for the production planning run. The
Objects
column displays the objects for which you can use the function.
Function |
Objects |
Settings |
Description |
---|---|---|---|
Deallocate |
Operations Orders Resources |
You use this function to remove orders from the resource schedule. |
|
Reschedule |
Operations Orders Resources |
Strategy profile |
You can use this function to: Schedule operations or orders that were deallocated Reschedule operations or orders that are affected by scheduling problems |
Fix objects |
Orders Operations |
You can use this function to fix the resource assignment and the dates/times of orders and operations. This ensures that the system cannot reschedule these operations or orders on other resources or dates/times in a subsequent processing step. |
|
Undo fix on objects |
Orders Operations |
You can use this function to undo the fixing of the resource assignment and the dates/times of orders and operations. The system can then reschedule these objects in a subsequent processing step. |
|
Transfer objects to the customer exit APOCDPS1 |
Operations Orders Resources Products |
In customer exit APOCDPS1, you can select the objects that you want the system to process (for example, schedule) in a production planning run processing step. |