Create Integration Model for Transferring R/3 Data You create an integration model for R/3 master data (BOM, routing, and master recipe) to transfer data to the SAP APO. During the transfer, the system generates a production data structure (PDS) that provides the basis for planning in SAP APO. You use the integration model to define what type of PDS is generated in SAP APO.
You can implement BAdIs that influence the results in SAP APO.
You have created the master data in SAP R/3 (BOM, routing, master recipe).
You have created a production version in SAP R/3 for each product that you wish to plan in SAP APO.
Do
not create a production version if you wish to create an integration model for a phantom assembly (option
Bill of Material
).
On the
SAP Easy Access
screen in SAP R/3, choose
Logistics
→
Central Functions
→
Supply Chain Planning Interface
→
Core Interface Advanced Planner and Optimizer
→
Integration Model
→
Create
.
The
Create Integration Model
screen appears.
At the top of the screen:
Enter a unique name in the
Model Name
field.
Enter the RFC destination you have defined for SAP APO in the
Logical System
field.
Enter a description in the
APO Application
field. This is for information only.
Choose the option
PDS (R/3)
and then
Further Restrictions
in theMaterial-Dependent Objects
group box.
In the
General Selection Options for Materials
group box, enter the materials, plant, and additional data for the product that you wish to transfer to SAP APO.
Depending on the data you require for planning in SAP APO, enter the following information in the
Production Data Structure
group box:
PDS Type
Determines what type of PDS is generated in SAP APO. You can implement BAdIs that can be applied to the generation.
Production Version
Determines which data is transferred.
Routing Select.
Determines which routing and master recipe is copied from the production version to the integration model.
The relevant PDS is generated in SAP APO based on the information provided in the
Production Data Structure
group box.
Choose
Execute
The
Create Integration Model
screen appears.
Save your data.
On the
SAP Easy Access
screen in SAP R/3, choose
Logistics
→
Central Functions
→
Supply Chain Planning Interface
→
Core Interface Advanced Planner and Optimizer
→
Integration Model
→
Create
.
The
Create Integration Model
screen appears.
At the top of the screen:
Enter a unique name in the
Model Name
field.
Enter the RFC destination you have defined for SAP APO in the
Logical System
field.
Enter a description in the
APO Application
field. This is for information only.
Choose the option
BOM
and then
Further Restrictions
in theMaterial-Dependent Objects
group box.
In the
General Selection Options for Materials
group box, enter the materials, plant, and additional data for the product that you wish to transfer to SAP APO.
Depending on the data you require for planning in SAP APO, enter the following information in the
Material BOM
group box:
PDS Type
Determines what type of PDS is generated in SAP APO. You can implement BAdIs that can be applied to the generation.
Usage
Determines which data is transferred.
Alternative
Determines which routing and master recipe is copied from the production version to the integration model.
The relevant PDS is generated in SAP APO based on the information provided in the
Production Data Structure
group box.
Choose
Execute
The
Create Integration Model
screen appears.
Save your data.
Master Data in R/3 |
Prod. Version Available |
PDS Type |
Possible Planning Selection |
BadI in SAP APO |
Result: PDS in SAP APO |
|---|---|---|---|---|---|
Bill of Material Routing Master Recipe |
Yes |
PP/DS |
Detailed Scheduling Rate-Based Planning |
/SAPAPO/ CURTO_ CREATE |
PP/DS PDS |
Bill of Material Routing Master Recipe |
Yes |
PP/DS with Subcontracting |
Detailed Scheduling Rate-Based Planning |
/SAPAPO/ CURTO_ CREATE |
PP/DS PDS in Suppliers / Subcontractor Locations |
Bill of Material Routing Master Recipe |
Yes |
SNP |
Detailed Scheduling Rate-Based Planning Sales and Operations Planning |
/SAPAPO/ CURTO_SNP |
SNP PDS |
Bill of Material Routing Master Recipe |
Yes |
SNP with Subcontracting |
Detailed Scheduling Rate-Based Planning Sales and Operations Planning |
/SAPAPO/ CURTO_ CREATE |
PP/DS PDS in Suppliers / Subcontractor Locations |
Bill of Material Routing Master Recipe |
Yes |
PP/DS |
Detailed Scheduling Rate-Based Planning |
/SAPAPO/ CURTO_ CREATE Method: CREATE_CTM_PDS |
CTM PDS |
Bill of Material (for Phantom Assembly) |
No |
PP/DS SNP |
No Influence on Generated PDS |
PP/DS PDS Without Routing |

If no routing has been specified in the production version, the system:
Generates an activity with the duration of the planned delivery time from the purchasing info record for a PDS with subcontracting in SAP APO.
Generates an activity with the duration of the planned delivery time from the product master for a PDS without subcontracting.