Backward Scheduling For optimization of the
objective function
values, the system schedules activities as early as possible. Under certain circumstances, activities are scheduled far from the requirements date/time, and this increases storage costs. In
backward scheduling,
which the system can execute after optimization, the system tries to schedule the activities to dates/times that are as close as possible to the requirements date/time in question.Starting from the requirements date/time in each case, the system searches
backward
for the next possible scheduling date/time and reschedules the activities.
If you want the system to execute
backward scheduling
during optimization, you must make the following settings in the optimization profile or when calling optimization:
Set the
Backward Scheduling
indicator on the
Basic Settings
tab page
On the
Additional Strategies
tab page, you define whether, in
backward scheduling,
the system is allowed to increase the
makespanachieved during optimization
.