Order Processing View Screen in
Production Planning and Detailed Scheduling
for displaying and processing an order.
In the order processing view, you can create, change, or delete an order . You create receipts for components for which you have defined manual planning in the product master. In the order processing view, you can display the order in its environment, which includes:
Pegging information
Status information
Alternative procurement options
Operations
The order tree is displayed on the left side of the order processing view.It consists of the order as the top node, as well as subnodes under which the actual order objects are listed.
Subnodes |
Order objects |
|---|---|
|
Products of the order |
|
Components of the order |
|
Operations and activities of the order |
By double-clicking an element of the order tree (node or order object), you control the content on the right side of the order processing view, as follows.
Node |
Content of the right screen area |
|---|---|
Order |
Header data of the order such as dates, alerts , and status information The SAP APO system displays the status of the order according to the status change made in the integrated OLTP system (for example,
On this screen you can: Set the conversion indicator to specify that the order is to be converted automatically after it has been transferred to the OLTP system Fix the output of an order to specify that automatic planning cannot change the order quantity The SAP APO system automatically sets the
|
|
List of the receipts of the order with the detail data, such as the availability dates/times and quantities. |
|
List of the requirements of the order with the detail data, such as the requirements dates/times and quantities. In this requirements list, the requirements are numbered using item numbers. |
|
List of the operations of the order with the detail data, such as dates/times and quantities. |
Order object |
Content of the right screen area |
|---|---|
Order product Component |
Product view , plus the following tabs: The
The
|
Operation |
Operation data, for example, resources being used, input and output products and relationships |
Activity |
Activity data |
You can call the order processing view either:
Directly in the
Interactive Production Planning
menu
In the receipts view and in the product view by double-clicking an order
The system performs
detailed scheduling
for an order using the
detailed scheduling strategy
, which you have specified under
Settings
.
The display of alerts for quantity and date problems is integrated in the order processing view. To display further alerts, for example, for resource problems, you can call up the Alert Monitor .
To display the quality of the planning based on your own criteria, you can call up the Plan Monitor .
To display the schedule of the orders in a Gantt chart, you can call up two differently configured DS planning boards from the order processing view. Here you can manually reschedule orders to different dates or resources or call the optimizer .