Query Standard Cost Estimate: Time Series for Multiple Materials, Price Comparison  Locate the document in its SAP Library structure

Technical name: 0COPC_C09_Q0005

Based on InfoCube CO-PC: Product Cost Planning – Released Cost Estimates (0COPC_C09)

Use

This query displays an overview of the released cost estimates for multiple materials across multiple periods in a single plant. To enable price comparisons on a uniform basis, the values of the cost estimates are converted from the costing lot size to a base unit of measure.

You can limit the number of materials displayed when you start the query. For example, you can limit the selection to a single material group. You can use all navigation attributes of the characteristic material to select the materials. For more information, refer to Filters below.

Note

This query is contained in the workbook Standard Cost Estimate: Time Series for Multiple Materials, Price Comparison.

For background information on the concept of queries, see Queries in Controlling.

Filters

This query restricts characteristics for which each value could have a cost estimate or cost component split for each material, costing date, and costing variant. Without these restrictions, the cost estimates or cost component splits would be added together in the query. For example, the cost estimates for the valuation views legal valuation and group valuation would be added.

Some characteristics were restricted to just one typical value. For the others, you must choose the value when you start the query. If you want to restrict characteristics to values other than the preselected values, copy this query and modify the copy accordingly. This can be particularly useful when you want to define a query that contains one of the following pieces of information:

InfoObject

Description (Restriction)

0CCOMPTYPE

Type of cost component split (fixed value main cost component split)

0CURTYPE

Currency type (fixed value 10, currency of company code)

0VALUATION

Valuation view (fixed value legal valuation)

0PLANT

Plant (variable 0P_PLANT; single value entry, required)

0MATERIAL__0MATL_GROUP

Material group (variable 0P_MATG; single value entry, optional)

Rows

InfoObject

Description (Restriction)

0MATERIAL

Material (variable 0S_MAT; selection options, optional)

Columns

Technical Name

Description (Restriction or Calculation Formula)

0FISCPER

Fiscal year/period (variable 0P_FPER; interval entry, required)

 

Price per unit = ( Fixed amount + Variable amount) / Lot size

The value of the cost estimate (based on the costing lot size) is converted to a base unit of measure.

Report/Report Interface

Query

Description

0COPC_C09_Q0002

Standard Cost Estimate: Detailed Report, Level/Lower Level Costs

0COPC_C09_Q0003

Standard Cost Estimate: Detailed Report, Cost Component Split

0COPC_C09_Q0006

Standard Cost Estimate: Detailed Report, Fixed/Variable Costs