Description of the Project
Your work with LSMW starts with the definition of the project as a unit of the data to be migrated.
...
1.
You create the
project from which you want to migrate data in the LSMW:
If |
Then |
The mapping and field assignments for a project are available in an SAP system (e.g. test system). |
You export
them from this system and import them into your SAP system. |
The mapping and field assignments for a project have been stored on a data carrier. |
You import them into your SAP System. |
You want to migrate data from your legacy system for the first time. |
You define the project. |
2. You define the subproject for a project or make it known to the LSMW by importing the mapping and field assignments (see above).
The project and subproject have been defined. Now you define the (business) object.