Start of Content Area

Process documentationDescription of the Project  Locate the document in its SAP Library structure

Purpose

Your work with LSMW starts with the definition of the project as a unit of the data to be migrated.

Process Flow

...

       1.      You create the project from which you want to migrate data in the LSMW:

If

Then

The mapping and field assignments for a project are available in an SAP system (e.g. test system).

You export them from this system and import them into your SAP system.
See Exporting a Project and Importing a Project

The mapping and field assignments for a project have been stored on a data carrier.

You import them into your SAP System.

You want to migrate data from your legacy system for the first time.

You define the project.
 

 

       2.      You define the subproject for a project or make it known to the LSMW by importing the mapping and field assignments (see above).

Result

The project and subproject have been defined. Now you define the (business) object.

More Information

Editing a Project

Editing a Subproject

Editing Objects

Maintaining Object Attributes

Where-Used List

 

End of Content Area