Entering content frame

This graphic is explained in the accompanying text Examples of Phase-In/Out Profiles Locate the document in its SAP Library structure

Phase-In

When defining a phase-in profile, you specify whether periods without a value should be set to 0 or 100. Here is an example of a 6-period phase-in profile with initial values being given a factor of 100. The factor before the start date is 0.

Period

-1

0

1

2

3

4

5

6

Phase-in time series

   

5

25

50

75

-

-

Original values

200

200

200

200

200

200

200

200

Factor for initial values

           

100

100

Factor before start date

0

0

           

Adjusted values

0

0

10

50

100

150

200

200

 

Phase-Out

When defining a phase-out profile, you specify whether periods without a value should be set to 0 or 100. Here is an example of a 6-period phase-out profile with initial values being given a factor of 0. The factor after the end date is 0.

Period

1

2

3

4

5

6

7

8

Phase-out time series

100

50

25

-

-

-

   

Original values

200

200

200

200

200

200

200

200

Factor for initial values

     

0

0

0

   

Factor after end date

           

0

0

Adjusted values

200

100

50

0

0

0

0

0

 

 

Leaving content frame