Function documentationSelection According to Calculated Dates

 

You can define a default query for a worklist whose selection is not based on fixed dates but for which the timeframe is calculated relatively in the future. You can select objects whose requested end will be reached in four weeks, for example.

Activities

  1. In Customizing for QIM under Start of the navigation path Worklists for Quality Issues and Activities Next navigation step Make Settings in POWL Cockpit End of the navigation path, open the POWL Administrator Cockpit (transaction POWL_COCKPIT).

  2. Select Standard POWL and choose Execute.

  3. Select the personalization application QIM_GQIA_POWL and choose Register Query.

  4. Select the query for which you want to define a calculated date and choose Maintain Query.

  5. If necessary, switch to change mode and choose Calculated Dates.