Import from Project System
You can import data from Project System to Portfolio Management. During import, the data of the project in Project System is mapped to the Project Management project that is linked to the portfolio item. Which data is transferred during import depends on the Customizing settings and the selections
you made under Data for Import
. The data of the project definition in Project System is mapped to the Project Management project definition. During import, the phase TASKHIERARCHY is created in the Project Management project below which the structure elements of the Project
System project are created.
Structural Mapping:
Project System |
Project Management |
Project definition |
Project |
WBS element |
Task |
Network header |
Task |
Network activity |
Task |
Network activity element |
Task |
Milestone |
Task |
Activity milestone |
Task |
Note
If you select Resources
during import, the system creates roles for network activities and network activity elements in the Project Management project. If you select Resource Assignments
during import, the roles in the Project Management
project are staffed by the resources of the work center assigned to the network activities and network activity elements.
You have linked the portfolio item to a Project Management project. You have accessed the Import Project
screen by choosing on the item details
screen on the Overview
view.
You select Project System
from the Application
dropdown list.
You select the Application System
.
You choose Browse
to select the required Project
.
You choose data for import by selecting one of the following:
Structure Only
Structure and Resources
Structure, Resources, and Resource Assignments
You choose Check
to display the messages that were caused by the import. Then you choose Import