The following table lists the dashboards and the features you can perform in these dashboards:

Work Center Dashboards

Create (new object)

Create Multiple

Delete

Different Views of Dashboard

Budget Status, Schedule Status, or Staffing Status

Related Items

Mass Update

Move To

Advanced Filter

Portfolio Structure

X

Items

X

X

X

X

X

X

X

X

Initiatives

X

X

X

X

X

X

X

X

Reviews

X

X

X

X

Collections

X

X

X

Determination of Icons in Item Dashboard

In Customizing for SAP Portfolio and Project Management, you can configure the icons that appear in the Item dashboard for Staffing Status, Schedule Status, and Budget Status. You can make those settings under Start of the navigation path Portfolio Management Next navigation step Global Customizing Next navigation step Portfolio Item Settings End of the navigation path in the activity Define Portfolio Item Alerts.

From the Item dashboard, you can click any icon to view more information about the status for that item. The logic for the determination of the status icons is explained here:

  • Staffing Status

    The staffing status for an item is determined depending on the values for total demand (for all roles) and total assignment (for all roles) with a given assignment unit for the following 12 months.

    The default logic for the staffing icon, which you can change in Customizing, is as follows:

    Assignment

    Icon

    Definition

    Assignment = 0

    Red

    Critical Under-Staffed

    0 < Assignment < Demand

    Yellow

    Under-Staffed

    Assignment = Demand

    Green

    Properly Staffed

    Assignment > Demand

    Yellow or Red

    Over-Staffed

  • Schedule Status

    The schedule status for an item is based on the ratio of completed tasks to-date to all tasks that are planned to be completed to-date. Each task is weighted by the number of planned hours it takes to complete and the percentage completion of the task.

    The table below shows the standard determination for schedule status. You can adjust the ratio ranges in Customizing.

    Ratio Completed

    Icon

    Definition

    0% - 49%

    Red

    Critical Behind Schedule

    50% - 89%

    Yellow

    Behind Schedule

    90% +

    Green

    On Schedule

  • Budget Status

    The budget status is based on the ratio of total actual cost to total planned cost. This data is transferred to SAP Portfolio and Project Management through the SAP FI/CO interfacing process and is displayed on the Project Details screen. The total actual cost is the sum of all actual costs posted in SAP FI/CO on the portfolio item cost collectors over the complete posting period of the associated PS project element.

    The budget icons in the Item dashboard are calculated on budget cost and actual cost in the following way. You can adjust the ratio ranges defining the status in Customizing.

    Criteria

    Budget Ratio Calculation

    Icons

    Definition

    For total planned cost > total actual cost

    Budget ratio = (total actual cost - budget cost ) / total actual cost * 100

    Red

    Yellow

    Critical Under Budget

    Under Budget

    For total planned cost <= total actual cost

    Budget ratio = (total actual cost - budget cost ) / budget cost * 100

    Green

    Yellow

    Red

    On Budget

    Over Budget

    Critical Over Budget

    To use period-to-date costs in the budget icon calculations instead of total actual costs, you can implement BAdI: Calculation of Portfolio Item Alerts in Customizing for SAP Portfolio and Project Management under Start of the navigation path Portfolio Management Next navigation step Business Add-Ins and Customer Includes End of the navigation path.