Horizontal Synchronization
You use horizontal synchronization to synchronize various aspects of objects between different applications: Portfolio Management
, and either Project Management
or Project System (PS)
). This means that
when you change an object in one application the same changes are carried out in the corresponding object in another application.
You have carried out the following Customizing activities for SAP Portfolio and Project Management
under:
All activities under:
It is possible to determine whether horizontal synchronization is carried out based on changes in Portfolio Management
(item-leading scenario), or changes in Project Management
or PS
(both project-leading
scenarios). It is possible to use both item-leading and project-leading scenarios at the same time.
In an item-leading scenario, any changes you make in Project Management
are not transferred to Portfolio Management
. Thus the process is controlled only fromPortfolio Management
.
Similarly, in a project-leading scenario, changes you make in Portfolio Management
are not transferred to Project Management
. Thus the process is controlled only fromProject Management
.
The table below outlines which objects in Portfolio Management
you can synchronize with which objects in Project Management
and PS
:
Portfolio Management |
Project Management and PS |
|---|---|
Item |
Project Management Project PS Project Definition |
Item Decision Point |
Project Management Project Phase PS WBS Element |
You determine which objects are synchronized (and in which direction) with regard to attributes, statuses, and (for Project Management integration only) authorizations.
When you create an item in Portfolio Management
based on a predefined item template or item type you can determine the Project Management or PS template or type that corresponds to this and is used to create the corresponding project. In addition, you can specify
which decision points in a particular item type or template are mapped to which phases or WBS elements in the corresponding project template.
You map item templates to Project Management templates and PS templates in Customizing for SAP Portfolio and Project Management
under .
You map item types to project types or project templates in Customizing for SAP Portfolio and Project Management
under .
Synchronizing Attributes between Portfolio Management and Project System
In Portfolio and Project Management
, you maintain the planned start date of the portfolio item. It is transferred to the start date of the PS project definition. This is an item-leading attribute.
In PS, based on the start date, the system schedules the project, including the assigned networks, in a bottom-up scenario. The system calculates the finish date of the PS project definition and transfers it to the portfolio item. The dates of the PS project WBS elements are also calculated and transferred to respective decision points of the portfolio item (project-leading attribute).