Distribution for Resource Management
You can use this function to change the resource assignment to roles.
You can specify start-and-end dates for the work effort and the amount of work to be distributed.
Field |
Status |
Explanation |
|---|---|---|
Valid From |
Mandatory |
Use the calendar to specify the valid from date for assigned effort distribution. |
Valid To |
Mandatory |
Use the calendar to specify the valid to date for assigned effort distribution. |
Assigned Effort |
Mandatory |
Specify the amount of assigned effort to be distributed during the above period. |
Unit |
Optional |
Specify the unit for the assigned effort. |
You can specify how the above work effort should be distributed:
Field |
Status |
Explanation |
|---|---|---|
Action for Assigned Effort |
Mandatory |
Select from the drop down list whether the assigned effort entered above, should be added, subtracted from or should replace the existing values. |
Period Type |
Mandatory |
Select from the drop down list how the assigned effort should be applied. |
To edit the distribution of a role, you navigate as follows:
Choose
Select a resource in the table to open the Resource Overview
fast entry screen. Expand the resource to drill down to the project and role. Select the role row and then choose Distribution
.
Choose
In the Staffing
work center, select a project in the table to open the Staffing Overview
fast entry screen. Expand the project to drill down to the role and resource. Select the resource row and choose Distribution
.
You can define the following for the distribution of a role or resource:
Start
and Finish
dates – indicates the period affected by the changes you make.
The icons specify whether the amount entered should be added to (Add), subtracted from (Subtract), or whether it should replace (Set) the existing amount.
The time unit may be different from the unit you used in resource-role assignment, but the system performs the necessary conversion for you.
Your selection in the Period Breakdown
field is the basis for the calculation. In the following examples, consider the work unit as hours.
Apply assigned effort to complete interval
In this case, the system calculates the daily average amount with applied assigned effort and the number of working days between the valid from date and valid to date. It then uses this to calculate the amount per month or week according to the number of working days in the month or week. This option applies the assigned effort according to the number of working days.
You have chosen Complete Interval
in the Period Type
field. The valid from date is November 1, 2005. The valid to date is December 28, 2005. You enter work effort of 360 hours. The system calculates the number of working days from
November 1 to December 28, which is 36 days (18 in November and 18 from December 1 to December 28 as per US calendar). The average daily amount, is 10 hours. The system adds, subtracts, or sets 10 hours for each working day in November and the working days from December 1 to December 28. This means that
the system adds or subtracts 180 hours in November and 180 hours in December for projects with a monthly time unit format.
For projects with weekly time unit format, the system adds, subtracts, or sets 10 hours for each working day of the week.
Apply work effort per month or week
In this case, the system applies a fixed amount to each month or week, regardless of the number of working days.
You have chosen Per Month
or Per Week
in the Period Type
dropdown list. The valid from date is November 1, 2005. The valid to date is December 28, 2005. You enter work effort of 40 hours, the system
adds, subtracts, or sets 40 hours in November and December for projects with a monthly format, even if November 2005 has 18 working days and December 2005 has 21 working days as per US calendar.
For projects with a weekly time unit format, the system adds, subtracts, or sets 40 hours for each week in November and the weeks from December 1 to December 28, despite the fact there are only three working days in last week of December.
Apply work effort per day
In this case, the system uses the work effort per day to calculate the amount of days per month or week. This option applies a fixed amount consistently, according to the number of working days.
You have chosen Per Day
in the Period Type
field. The valid from date is November 1, 2005. The valid to date is December 28, 2005. You enter an amount of 10 hours. The system adds, subtracts, or sets 10 hours for all working days
in November and for all working days from December 1 to December 28. This means that the system adds or subtracts 180 hours in November, and 180 hours in December for projects with a monthly time unit format.
For projects with a weekly time unit format, the system adds, subtracts, or sets 10 hours for each working day of the week.