Cost Estimate Without Quantity Structure:
Process Flow
You can create a cost estimate without quantity structure for a material that does not yet have a PP quantity structure. For such materials, you create a quantity structure using a unit cost estimate.
You can also use existing data for material cost estimates without quantity structure, data such as materials, internal activities, work centers, material cost estimates, and base planning objects.
You have checked the settings in the costing variant. For more information, see Preparation for Base Object Costing.
...
1. You create a material cost estimate without quantity structure using a costing variant as the basis for costing.
For more information, see Creating a Cost Estimate Without Quantity Structure.
2. You enter the costing data manually using the unit cost estimate.
For more information, see:
¡ Creating Cost Estimates with Reference and Copying a Cost Estimate
¡ Origin of Data in Unit Costing

As an alternative to single-level unit costing, you can edit the cost estimate without quantity structure on a multilevel basis. For more information, see Multilevel Unit Costing.
3. The system determines the prices for materials and internal activities as well as overhead and process costs.
For more information, see:
¡ Use of Existing Costing Data
4. You analyze the results and save the cost estimate.
For more information, see:
¡ Saving Material Cost Estimates
5. You can update the costing results in the material master record, and transfer them into Profitability Analysis.
For more information, see:
¡ Purpose of Product Cost Planning
6. You can archive and delete material cost estimates.
For more information, see:
¡ Archiving Material Cost Estimates