The following statuses exist for the project definition:
Status |
Meaning |
Created |
The project has been created in the system (initial status). |
Released |
|
Locked
|
The project is temporarily protected against changes. You can set the status at the same time as the status Created or Released. |
Completed |
The project has been completed. |
Canceled |
The project was not completed successfully. If a project is canceled, project role staffings after the date the project was canceled are also canceled. |
To Be Archived |
The project can be archived. |
Flagged for Transfer |
The project is selected for transfer to SAP ECC. This status is only relevant if you selected an automatic controlling method for accounting integration. |
To Assign |
The project is selected for transfer to SAP ECC. This status is only relevant if you selected a manual controlling method for accounting integration or have switched to manual assignment. |
Transferred |
The project has successfully been transferred to SAP ECC. |
Assigned |
The project has successfully been assigned. |
The following dependencies exist between the status of phases and the status of the project definition:
● The release of the project definition leads to the release of the first phase of the project. Phases can only be released if the project definition has been released and is not locked.
● Phases may only be added, modified, or deleted if the project definition has the status Created or Released. New phases cannot be inserted before or between phases that have already been approved.
● Once a phase has been approved, the next phase is released.
● If a phase has not been approved, the project cannot be completed, only canceled. The next phase is not released.
● Locking a phase does not influence the status of the project definition. When a project definition is locked or unlocked, the status Locked is not set or removed for the released phases.
● The project definition can only be completed if the last phase has been approved.
● If a project definition, phase, or template is locked, no dependent data (for example, checklist items) can be changed either. The project definition can only be unlocked.