Object documentation Status of Tasks  Locate the document in its SAP Library structure

Definition

The following statuses exist for tasks:

 

Status

Meaning

Created

The task has been created in the system (initial status).

Released

See Releasing Project Elements.

In Process

The task is processed, actual data is confirmed.

Completed

The processing of the task is completed.

Canceled

The task is not completed successfully.

If the task is canceled, the subtasks are also canceled.

 

Integration

The following dependencies exist between the status of phases and the status of tasks:

·        The release of the phase leads to the release of all the tasks. It is possible to release tasks before releasing the phase.

·        Locking a phase does not influence the status of the tasks. However, it is not possible to process the tasks if the phase is locked.

 