Procedure documentation Scheduling a Task  Locate the document in its SAP Library structure

Use

You use Task Planner to schedule operations to be executed automatically based on the date and attributes defined during the task definition. You can schedule a new task(s) such as starting an application service, to occur once or repeatedly (a recurring task).

Note

A recurring task is a task that can repeat at regular intervals based on the date and attributes defined during task definition.

Procedure

...

       1.      In the Task Planner Overview area, choose New Task.

The Task Definition view is displayed.

       2.      Enter the task name.

       3.      Enter the start date (or choose a date value from the date picker) on which the task should be executed.

Note

The date should comply with the time zone where the ACC application is deployed.

       4.      Enter the time when the operation should be executed.

Note

Since the time format is different in different locations, the format should comply with the local setting format. For example, the English format could be one of these: 9:11:12 AM, 9:11 AM, 091112AM, or 0911AM.

       5.      Choose the relevant frequency:

                            a.      If you want to execute the task once, select One Time Action.

                            b.      If you want to schedule a recurring task, select Periodic Action on Every.

                                                  i.       Select the day(s) on which the task should be executed.

The task is executed on the selected day every week.

       6.      Assign relevant action(s) to the task.

                            a.      In the Action List area, choose Add.

                            b.      Enter the application service name or choose the relevant application service using Advanced Search.

                            c.      Select an action from the Action dropdown list. The action can be Start, Stop, or Relocate.

                            d.      If the Action is Start or Relocate, enter a resource name or choose the relevant resource using Advanced Search.

Note

If you want to remove an action, choose Remove.

       7.      Choose Save to save the task.

Result

You have now scheduled a new task and the action(s) defined for the task are executed based on the defined attributes.

You can view the following details in the Task Planner view.

Field

Description

Task Name

Task name.

Date

Date on which the operations defined for the task are executed.

Time

Time during which the operations defined for the task are executed.

Recurrence

If selected, the task is recurrent.

Resp. User

Name of the user who created or last edited the task.

Status

Displays one of the following status for the tasks (future or completed tasks):

·        Red (Failed): At least one of the task actions returned an error and all the further actions are canceled.

·        Yellow (Warning): The task is executed successfully, but one or more of its actions reported a warning.

·        Green (Successful): The task is executed successfully without any warnings or errors.

·        Gray (Not available): The task is assigned for future execution.

 