Procedure documentation Defining Runtime Views  Locate the document in its SAP Library structure

Use

Guided Procedures (GP) enables process contributors to check different aspects of a process at runtime by means of different views.

You can configure the available runtime views when designing the process template.

Procedure

...

       1.      In the gallery, select the relevant process template, and open its design time.

       2.      To switch to edit mode, choose This graphic is explained in the accompanying text (Edit).

       3.      Open the Select Views tab page.

       4.      You can add the following view types:

¡        Generic views

The GP framework provides a set of predefined runtime views, which you can use. The following table provides an overview of the available generic views and the information they provide.

Generic Views

View

Description

Comments

Additional Resources

Additional Resources (with You Can Navigator)

Enables you to see:

      attachments added to the process in the design time Attachments can also be added at runtime.

      process activities you can execute

      info callable objects added to the process (if any)

      ad hoc items (if any)

More information:

Attachments

Overview

Overview (with Process Control Navigator)

Enables you to see:

      overview information about the process steps and status

      process control elements (if any)

Process Activities

Process Activities (with Activity Navigator)

Enables you to see:

      current activity

      process steps

Process Activities

Process Activities (with Activity Navigator and You Can Navigator)

Enables you to see:

      process steps

      info callable objects added to the process (if any)

      ad hoc items (if any)

This is the default view that is added to the process template initially.

Process Activities

Process Activities (with Activity Navigator by You Can Navigator)

Enables you to see:

      current activity

      process steps

      info callable objects added to the process (if any)

      ad hoc items (if any)

Process Activities

Process Activities (with Activity Navigator, Process Control Navigator and You Can Navigator)

Enables you to see:

      current activity

      process steps

      info callable objects added to the process (if any)

      ad hoc items (if any)

Process Activities

Process Activities (with Mini Phase Navigator, Activity Navigator and You Can Navigator)

Enables you to see:

      current activity

      process phases

      process steps in each phase

      info callable objects added to the process (if any)

      ad hoc items (if any)

Process Information

Process Information (with You Can Navigator)

Enables you to see:

      information about the process, blocks, and action, such as processors, deliverables, and so on

      info callable objects added to the process (if any)

      ad hoc items (if any)

More information:

Info Callable Objects

Ad-Hoc Items

¡        Custom views

Additional views can be implemented as well. You can add them using Add Custom Views.

       5.      Select the default view that to be displayed initially when the process is started.

       6.      Choose This graphic is explained in the accompanying text (Save).

Note

You can remove a view by selecting it and choosing Remove View.

However, at least one view must be defined for a process.

Result

At runtime, process contributors may switch between the predefined views.

 